Space moves 2018 programme: refurbishment
Value: £670,000 (gross) | Timescale: 30 April 2018 - 21 September 2018
Over the Easter and Summer vacation periods a series of dependent moves and refurbishments are being carried out to upgrade space and improve the University space utilisation. The University Finance space has been remodelled to enable co-relocation of HR to neighbour office suite that has in turn release space in Dorothy Hodgkin building to provide new pool teaching space. In addition the neighbouring Lecture Theatre is being upgraded with new LED lighting, theatre seating, IT network and audio visual equipment. Works also shortly to begin in the University Library basement to create additional silent study space in readiness for new academic year.
Programme is currently running to time and budget.
Existing DH0.21 Lecture Theatre due to be upgraded:
Progress images